Tag Archive for: Collins class

How the Collins submarine fleet went from near zero to hero

For most of the past decade, Australia’s six Collins class submarines have provided the nation with a fine underwater warfare capability. Designed to meet operational requirements beyond the capabilities of other conventional submarines, the government of the day has been able to rely on the availability of several highly capable submarines.  

But it hasn’t always been that way. In fact, it was nearly 20 years after the delivery to the navy of the first of type, HMAS Collins, before the navy and government could reliably plan around the availability of submarines that were fit for purpose. For a long time, more than $10 billion of investment had provided the nation with very little payback in terms of a credible defence capability. Submarines spent years out of commission and availability across the fleet dwindledsometimes to near zero.

The story of how the Collins class was finally brought up to a high standard of reliability is the subject of my new ASPI report, Nobody wins unless everybody wins: the Coles review  into the sustainment of Australia’s Collins class submarines. 

The problems with the Collins class began early. The building and delivery of the boats became highly politicised and the negative aspects that can reasonably be expected from any complex projectcost overruns, schedule slippages and technical problems that take time and effort to resolvebecame consistent headline fodder. ‘Dud subs’ was a label that stuck. 

That perception could have been put to bed once all the bugs had been ironed out and the submarines successfully put into use. After all, the original project problems with the F-111 were also well publicised and the subject of political point-scoring and public discontent with the cost. But once in service, the fuss died down, and the F-111 became something of a favourite at air shows and public displays—to the point of there being quite a bit of grumbling when they were retired. 

Instead, in the years following the delivery of the last of the Collins class in 2003 and the resolution of most of the remaining technical issues, a new set of negative headlines started to appear. Partly through publicly available sources and partly through leaks from disaffected people within the submarine service and industrial support base, the parlous state of the fleet was revealed. A series of studies and reviews over the years—as many as 18 by some counts—identified issues and made recommendations but nothing seemed to make a lasting impression.  

Within the world of submarine management, relationships between the operator (the navy), the contractor (ASC, a government-owned enterprise based in Adelaide owned by the Department of Finance) and the group within the Department of Defence responsible for project management (the Defence Materiel Organisation—DMO) had become highly dysfunctional and occasionally outright hostile. 

By 2011 it was clearly that something drastic had to be done. The long lead time for the Collins class replacement meant that discussions for the successor class needed to start and early decisions about the direction of that project would be required. But it simply wasn’t possible to get traction on another very expensive submarine project when the existing fleet was essentially moribund—it would seem a case of throwing good money after bad. 

The answer was for the government to sponsor yet another review. Many observers at the time (including me) were sceptical that another such exercise was unlikely to do much more than rearrange the proverbial deckchairs. In my ASPI role at the time I spoke to many of the key individuals involved. Opinions varied on many points of detail, but there was a unanimous view across the entire enterprise that it was someone else’s fault. Many meetings were called, with the usual outcome being that the warring parties would have another meeting at some future time. In between those meetings, metaphorical wagons were circled and arguments marshalled for future stoushes.  

Many of the key players are quoted in my new report, and their views are often expressed quite candidly. That’s because at heart the woes of the submarine fleet were due to organisational issues and the breakdown of trust between the parties. The maintenance people at ASC felt that they were being micromanaged by the DMO to the point of not being able to do what they needed to do. The DMO felt that ASC were taking advantage of a contract that paid them whether or not the submarines were being maintained efficiently. The navy, ultimately the customer for submarine availability, didn’t have a clear understanding of what it could expect from a fleet of six submarines—and didn’t have a clear statement of its requirements in any case. 

The review team that was put together was headed by John Coles, a British naval architect and engineer who had already established a track record for sorting submarine maintenance problems in the United Kingdom. The team was formidable—it wasn’t a consultancy group of generalists, but a small group of career professionals with hard-won specialist knowledge in submarine sustainment. That was to prove a crucial factor in the success of the review—the deep understanding of the business within the review team meant that nobody could pull the wool over their eyes.   

It didn’t take Coles and his team long to work out that the Collins class submarines were fundamentally sound but the system (being generous with the term) put in place to support them wasn’t fit for purpose. And they also found that everyone wanted to fix the problem but that nobody agreed on what the causes of the problem were. 

The whole story was a fascinating one to pull together. I’d tracked the facts and figures over the years, often reporting them here on the Strategist. And I’d been buttonholed at ASPI and Defence functions by enough people anxious to explain why those other guys were to blame to know that there were deep cultural divides at play.

The new ASPI publication explains how the ‘Coles review’ (as it became universally known) solved the problem. There was no magic formula: the answer was to work out in detail what needed to be done, who was best placed to do it, and then make sure that the delegated authorities and accountability mechanisms were in place to let them get on with it. The title of my report comes from Coles’ approach of making everyone a winner by enabling them to kick the goals they needed to kick while others did the same. 

The improvement that followed the review and its implementation was swift and dramatic. The review did a comparative study of six other submarine-operating nations and found that Australia’s performance was by far the worst. In a couple of years, that had turned around to the point where Collins submarine availability exceeded the international benchmark, to the relief and delight of everyone involved. 

There’s much more to the story than this brief overview, and there are lessons that go well beyond the narrow task of submarine sustainment. I hope the report gets widely read within the departmental and industrial organisations responsible for managing defence projects and delivered capabilities.

In particular, I hope those charged with the even more demanding task of preparing for Australia to get into the business of supporting, operating and one day building nuclear-powered submarines appreciate what they are getting into. As the experience with the Collins class showed, buying the hardware—however expensive and complicated that process can be—is only the beginning.

Planning defence projects for a new submarine era

Despite negative perceptions about the Collins-class submarine project, the six boats now in service with the Royal Australian Navy are regarded as among the world’s best diesel-electric submarines.

While the project faced major delays and cost overruns, it ultimately became a significant sovereign defence industry capability and provides an excellent basis for the challenging AUKUS nuclear-powered submarine (SSN) program.

Timing is everything. From the Collins project’s inception in 1983, it took 20 years to commission the sixth and last boat, HMAS Rankin, seven years later than planned. Three decades on, the AUKUS SSN program presents a substantially larger and more complex delivery challenge and carries a risk of program delays causing considerable capability gaps for the Australian Defence Force.

The replacement of the Oberon-class submarines (in service since the late 1960s) wasn’t urgent in terms of immediate regional threats. Between 1993 and 2003, Australia’s geopolitical priorities involved strengthening its alliance with the US in supporting various military operations such as the Gulf War and the wars in Afghanistan and Iraq. In parallel, Australia was also focused on local regional instability and played an active role in peacekeeping missions to Solomon Islands and Bougainville and the East Timorese independence process.

Today, as outlined in the 2023 defence strategic review, Australia faces a new global order. While our alliance with Washington remains central to our security and strategy, the US is no longer the Indo-Pacific’s unipolar leader. The likelihood of conflict and threats in our region has never been higher.

The declining warning time emphasised in the review and the pressing need for Defence to deliver large capability and infrastructure projects quickly leave little room for delays in delivering the SSNs.

Defence capability and infrastructure projects have frequently encountered significant delays. The Australian National Audit Office’s 2021–22 major projects report found that there had been a total of 1,363 months (equivalent to 113 years) of slippage across 34 projects. Naval projects accounted for five out of the seven projects with the most serious delays.

Defence has faced a significant loss of crucial planning time in replacing the Collins, spanning at least 15 years from the initial identification of the need for a future submarine in the 2009 defence white paper. This period includes the cancellation of the Attack-class submarine project with France and its replacement with the plan for AUKUS SSNs in September 2021, which added a major delay.

The AUKUS SSN program surpasses the complexity of the Collins project, which involved one European partner and infrastructure works at HMAS Stirling and the Osborne shipyard. AUKUS is a trilateral partnership underpinned by complex intellectual property and technological transfers, regulatory compliance and political considerations. The SSN program requires extensive infrastructure works across Australia (and overseas).

Nearly a year after the AUKUS SSN announcement, there’s still uncertainty about how Defence is preparing for and prioritising multiple supporting infrastructure projects. This poses a risk that industry might not have the capacity to deliver within the required timeframes.

On the surface, the proposed infrastructure works at HMAS Stirling and the Henderson and Osborne shipyards seem easy given that they are existing facilities used to sustain the Collins boats.

Upgrades to wharfs, warehousing and sustainment facilities at HMAS Stirling are crucial to ensure that it can accommodate the Submarine Rotational Force–West, docking Collins, US Virginia class, and UK Astute-class boats. While the works are due for completion in 2027, interim arrangements may be needed to accommodate the Virginias, which are 38 metres longer and 2.8 metres wider than the Collins.

Significant investment in the Osborne shipyard is planned to manage the Collins life-of-type extension from 2026 to 2038 and the production of new submarines from the late 2030s to 2055. These facilities won’t be required until the late 2020s.

As has been noted recently, establishing a new east coast nuclear submarine base will require significant planning and time. Naval bases are large, complex precincts. HMAS Stirling took more than a decade to develop, while Darwin’s HMAS Melville took six years. The shortlisted options are commercial ports, which will mean additional time to engage with stakeholders, develop agreements and undertake land transfers and land-acquisition processes. Should the project be referred for Environment Protection and Biodiversity Conservation Act approval (which is highly likely given the potential sites’ current uses), that could add more than 12 months to the planning process. If the east coast base is to be operational before Australia’s first Virginia arrives in 2032, site selection will need be finalised in accordance with Defence’s proposed timeframe of late 2023.

Like the east coast base, establishing supporting nuclear training, storage and waste-disposal facilities, even on Defence land, demands extensive planning for design development and approvals. This includes environmental approval, regulatory approval through the Australian Radiation Protection and Nuclear Safety Agency, public consultation and additional approval if the site is located on or near Indigenous land. If a preferred site is rejected, restarting the process will eat up more time.

The SSN sustainment facilities introduce additional planning complexity. It’s not clear if the torpedo maintenance facilities at HMAS Stirling are able to maintain the navy’s Mk48 ADCAP torpedoes, or if their maintenance will be brought back to Australia from Pearl Harbor. As speculated in The Australian, it’s unclear if Tomahawk missiles will be procured and, if they are, where they’ll be stored and maintained. No doubt that will be addressed with the guided weapons and explosive ordnance program.

The defence strategic review acknowledges the need to prioritise AUKUS infrastructure in line with SSN delivery and commissioning schedules while considering constraints in the construction industry and the need to align with pre-existing works. Addressing the challenge of industry’s capacity to deliver is crucial for Defence, necessitating forward notification and adherence to procurement timeframes.

In the next decade, the defence construction sector will experience a surge in demand driven by AUKUS infrastructure needs and other significant defence projects, including the $3.8 billion commitment to upgrade facilities in northern Australia.

To support industry’s capacity to meet these demands, it’s crucial for Defence to share and adhere to its infrastructure timeframes, empowering industry to prepare and deliver on time. Defence should also be prepared to manage unexpected risks—as demonstrated in the past four years with the impact of the global pandemic on the construction industry through labour shortages, international supply chain disruptions and, in some cases, liquidations.

Last week at the ADM Defence + Industry Conference, Defence Minister Richard Marles advised that procurement ideals would be known when the government’s defence industry development strategy was ready to share with industry next year. To quote management expert Peter F. Drucker, ‘Unless [a] commitment is made, there are only promises and hopes, but no plan.’

Australia’s submarine acquisition is about deterrence, not aggression

While we await the AUKUS partners’ announcement of their plans for Australia to acquire nuclear-powered submarines (SSNs), the public discourse on the agreement has become wildly out of sync with reality.

Charges that Canberra’s SSN program might promote conflict with Beijing or start a nuclear arms race need to be evaluated far more critically. Key to understanding the impetus for the trilateral agreement are considerations driven by the regional dynamics of military acquisitions as well as international agreements on the control of nuclear material.

Uncritically accepting the positions put forth by Beijing and Moscow would not only mean Australia abrogating its sovereign right to make decisions about its own national defence but also be detrimental to the interests of Southeast Asian nations. Acting Prime Minister and Defence Minister Richard Marles and opposition leader Peter Dutton both told parliament yesterday that acquiring the submarines was about maintaining peace in the region rather than going to war.

Submarines have been a regular presence across the Indo-Pacific for decades. Indonesia, one of the more vocal critics of Australia’s plans, operated the largest submarine fleet in the region in the 1960s and 1970s with a force of 12 Whiskey-class diesel-electric submarines obtained from the Soviet Union. Today, its submarine force numbers four, following the tragic loss of KRI Nanggala in 2021. The Royal Malaysian Navy operates two Scorpene-class submarines. Singapore has four submarines and has placed orders for an additional four modern boats. Vietnam has six modern Kilo-class submarines purchased from Russia. Thailand and the Philippines are actively pursuing submarines, although Bangkok’s planned purchase of Chinese Yuan-class boats appears to be foundering. So, in maritime Southeast Asia, only Cambodia and Timor-Leste aren’t operating or actively pursuing submarines as part of their maritime strategies.

It seems safe to assume that none of these states consulted Canberra while developing their submarine programs. However, both Malaysia and Indonesia have voiced their opinions that Australia’s pursuit of SSNs risks a regional arms race—while remaining painfully silent on the subject of an unprecedented naval expansion to the north being carried out by the People’s Liberation Army Navy. Somehow submarines that don’t even exist yet have caused more regional consternation than a scores-strong fleet that is not only nuclear-propelled but armed with nuclear weapons as well.

It is the height of hypocrisy for the Chinese government to hyperventilate over a nuclear-powered submarine program in Australia when the PLA Navy has commissioned at least 15 nuclear-powered boats in the past two decades, several of which carry nuclear-tipped intercontinental ballistic missiles. The Chinese sub fleet is projected to grow by at least 10 by 2030. Under Australia’s plan, the Royal Australian Navy may only start receiving its new submarines by that point. In the meantime, Australia’s ageing Collins-class boats will likely need to serve well past their intended decommissioning dates. In fact, one of the key questions that the AUKUS partners are expected to answer next week is how Australia will avoid a submarine capability gap.

Beijing’s disingenuous talking points have also surfaced in Russian circles. Russian officials have implied that an Australian SSN  program will weaken the international non-proliferation regime and contribute to an acceleration of the imagined arms race. In fact, the Treaty on the Non-Proliferation of Nuclear Weapons doesn’t restrict non-nuclear-weapon states from developing ships or submarines powered by nuclear reactors; nor does it have provisions for overseeing the nuclear material committed to such a program.

It is equally incredible that the Russian government would criticise a state for embarking on an SSN program when the Russian Navy already operates a significant fleet of SSNs itself and has leased some of them to India. Having repeatedly threatened to use nuclear weapons as part of its illegal invasion of Ukraine, Moscow should be perhaps the last capitol on earth to criticise Australia for seeking a completely legal nuclear-propulsion capability for its own navy.

Australia has taken great pains to assuage concerns across Southeast Asia, reiterating its commitment to the Nuclear Non-Proliferation Treaty and attempting to correct misperceptions about the nature of AUKUS—namely, that it is a technology-sharing mechanism, not an operational network or alliance.

Technology sharing among partners is normal across the globe, including among the states that are the biggest critics of the AUKUS partnership. It appears, rather, that those states using their navies to impose their will upon their neighbours, from Russian naval strikes against Ukraine to Chinese ships enforcing illegal claims at sea, are effectively demanding that the world ignore their aggression and remain vulnerable to their military expansions.

With a full grasp of the facts, it’s plain that accusing Australia of contributing to an arms race is absurd, particularly when an aspiring regional hegemon already has 11 times Australia’s submarine strength in a navy seven times bigger than the RAN. An arms race requires at least two competitors, but there’s only one state in the Indo-Pacific that’s sprinting toward expanding its naval power—and that is China.

Asia has enjoyed a long period of relative peace and prosperity that is increasingly jeopardised by China’s intimidation campaign at sea and by its threats of violent invasion of Taiwan. Some regional powers, such as India, Australia, Japan and the United States, are eager to deter China from undertaking a catastrophic war of aggression that would upend the world economy. The measures required to deter China—which include developing modern military capabilities commensurate with those already possessed by Beijing—will necessarily generate some discomfort in the short term as China attempts to intimidate states into inaction. However, rather than adopt Beijing’s talking points, regional states might well consider what the regional order would look like should war not be deterred.

AUKUS holds out the promise of an extension of the Asian peace and a reduction in the likelihood that China will use its rapid and massive military expansion to resort to naked aggression. The AUKUS initiatives are designed to foster peace and stability in the region by maintaining the long-term regional military balance, which is surely worth enduring a bit of short-term discomfort.

Unpacking the (semi-)announcement of a submarine base on Australia’s east coast

One of my colleagues told me on Monday morning that we were going to get a ‘semi-announcement’ on Australia’s submarine basing that day. The government has been making quite a lot of semi-announcements lately about defence capability; I think we’re up to semi-announcement number three on the long-range anti-ship missile and it’s still not clear what capability we are going to get, or when.

Since its announcement of AUKUS and its intention to acquire nuclear-propelled attack submarines (SSNs) in September last year, the government has also been doing some ‘semi-messaging’ on the submarine enterprise. Defence Minister Peter Dutton has been semi-messaging that we’re going to get SSNs much earlier than the late 2030s date first suggested by the government, though he hasn’t said how that’s going to happen. He also semi-messaged on the ABC on Sunday that the government might make an announcement about its choice of SSN before the election, nearly a year before the nuclear submarine taskforce is due to make its recommendation to the government.

So, what did we get on Monday—a semi-announcement or an honest-to-goodness announcement with some new news and actual information that indicates real progress on the SSNs?

As always, a little historical context is helpful. We’ve known since the Rudd government (semi-)announced in 2009 that it intended to double the size of the Royal Australian Navy submarine fleet to 12 boats that we’d need an east coast submarine base. The navy has done sterling work in increasing its submariners to 800, the number needed for its six Collins-class boats. But the Defence Department’s analysis has repeatedly shown that getting to at least 2,000, the number needed for a larger fleet of bigger boats, would require access to larger population centres on the east coast to support recruitment and retention.

That’s the primary driver for an east coast base. There are other ones. Two bases give redundancy, which is very useful now that Australia sits under the umbrella of China’s long-range strike capability. The east coast also gives better access to much of the Pacific without needing to navigate the straits and shallows of the archipelago to our north.

It’s not surprising, then, that an east coast base had been baked into the submarine plan, even before the Attack-class was cancelled. That’s why there’s already $10 billion provisioned in Defence’s 2020 force structure plan under the euphemistic title of ‘Undersea Warfare Support Facilities and Infrastructure’.

Over the years, Defence has done a lot of studies into the optimal location for an east coast submarine base. The problem is that all the good sites are already occupied. Every site has advantages and disadvantages and there’s no stand-out candidate. So, it’s not surprising that each study has reached different conclusions. The usual candidates are Brisbane, Newcastle, Sydney, Port Kembla and Jervis Bay.

Sydney is now out because it just doesn’t have the spare real estate for a fleet of SSNs, plus no government wants to pick a fight with the wealthy and influential people who ring the harbour and don’t want to live next to nuclear reactors. Also, shutting down a city of five million should an accident happen is not a pleasant prospect. Jervis Bay is out because every tree-hugging, bird-watching nature lover in the country (including me) would fight it. So that just leaves Brisbane, Newcastle and Port Kembla.

So, if this was all part of the plan already and all the government has done is rule out a couple of locations, does that mean Monday’s news was only a semi-announcement? Not really. It’s actually a significant statement. No government has previously said so clearly that it intends to develop an east coast submarine base. That’s important because it allows us to start the two conversations we have to have. The first is about how Defence can gain access to real estate that is likely already occupied. That will require finding a way to encourage the current occupants to leave. Some of them could be thinking about moving already; coal ports such as Newcastle and Port Kembla might be very keen to have a large defence facility whose economic impact could help ease the pain of the impending transition to the post-carbon economy.

That gets us to the second, but probably even more difficult, conversation. Generally, local communities are eager to host Australian Defence Force facilities. But many people simply don’t want nuclear reactors in their harbours, regardless of the impeccable safety records of the US and UK nuclear submarine programs. And there are fears about becoming a strategic target (see earlier point about Chinese strike capabilities). Those concerns figured in the immediate reaction to Monday’s announcement. That aversion will be reinforced if Defence can’t develop a long-term disposal plan that doesn’t involve rusting submarines and their reactors sitting for decades in port before they can be dismantled.

This is where the government and Defence need to lift their messaging game. The original AUKUS announcement came out of nowhere with no consultation. For the average person in the street, so did the one about the east coast base. If the government and Defence want to bring the Australian public with them on the long journey to acquiring an SSN capability, they will need to engage rather than just announce.

But Monday’s news also had elements of the semi-announcement to it. Key details such as which functions will be conducted at the new base were left out. Whether deep maintenance will still be done in Adelaide or moved east is an interstate stoush that the government has no interest in unleashing right before an election. And there was little to suggest that Defence is close to developing the information needed for a decision on the location, function and construction schedule of the base. Prime Minister Scott Morrison said that initial work on the basing decision would be completed by the end of 2023—that’s nearly a year after the submarine taskforce is meant to report back to the government with its recommendation on the best pathway to an SSN capability. Announcements are not the same as information.

As for the semi-messaging that the government’s choice of submarine could be announced ahead of the election, the prime minister hosed that down in the question and answer session after his speech to the Lowy Institute on Monday. A year and a half is not a lot of time for the submarine taskforce to answer a long list of very difficult questions that they need to get right. It’s probably best to let them use it.

What’s the real cost of Australia’s submarine capability?

You can have a cheap submarine capability, or you can have a safe and effective one. There’s no third option. Australia has chosen the second option; consequently, its submarine capability costs a lot. But how much exactly? We’re all now very familiar with the $89 billion price tag on the future submarine, but that’s a number that stretches far off into the distance, and it doesn’t cover all aspects of the capability.

Perhaps a more useful way to answer the question is to focus on the annual spending on Australia’s submarine capability. Parts of the answer are easy to find, but as with all areas of Australian Defence Force capability, it’s difficult to develop a comprehensive number. It’s particularly hard if we’re trying to include all elements of capability—or the nine fundamental inputs to capability, to use the Defence Department’s term—such as facilities. It’s hard to know how much of the $3,188 million spent annually on estate maintenance and garrison support should be attributed to submarines, for example. Or how to identify indirect costs such as educating future submarine officers at the Australian Defence Force Academy. So we’ll limit our analysis to direct costs that can be attributed to submarines with reasonable confidence.

The sustainment cost of the navy’s six Collins-class submarines is the easy bit. That’s spelled out clearly in Defence’s budget statements and annual report. It’s averaged $574 million per year over the past 10 years but has been increasing. It’s predicted to be $671 million this year.

However, that number doesn’t include some key elements. One is fuel. A full tank of diesel will cost several hundred thousand dollars. Another cost that isn’t included is even bigger, namely the uniformed personnel operating and maintaining the submarines. While each submarine has a crew of around 55, a much larger number than six lots of 55 is needed to have a robust, sustainable workforce. The navy has done well in increasing the number of its submariners over recent years and Defence informed the Senate earlier this year that that total had reached 881, although there were still some shortfalls. ASPI analysis (page 70) concluded that the average cost of each permanent ADF member was $160,000 a year five years ago, but submariners receive special allowances and retention bonuses so we could be looking at $250,000. Overall, the cost of the uniformed submarine workforce is probably more than $225 million.

The Collins sustainment cost includes full- and mid-cycle dockings in which the submarines are taken out of the water for overhaul, but it doesn’t include the cost of major upgrades that are installed during those dockings. Those are listed separately as acquisition projects in the SEA 1439 portfolio of projects. Here’s where numbers can get tricky. Since the Defence budget statements include only the department’s top 30 projects by planned spending for the year, we don’t know projects’ spending if they don’t make the cut-off, which was $97 million this year (although it’s been lower at around $50–60 million in recent years). If a project doesn’t ever make the top 30 it’s hard to know that it even exists, let alone what it’s spending.

Projects currently running include SEA 1439 Phase 6, which is upgrading the Collins’ sonars. It spent $133 million in 2020–21 but doesn’t make the top 30 this year. There’s also SEA 1439 Phase 5B2, which is an upgrade of the Collins’ communications and electronic warfare suites. It spent $64 million in 2018–19 and $70 million in 2019–20. There are other phases of SEA 1439, but we can’t see what they are spending. This year the budget statements also include Joint Project 9013, which is upgrading the Collins’ satellite communications system with predicted spending for the year of $101 million. We’ve collated the available data in our Cost of Defence database. Let’s lump all of the Collins upgrade projects together and call it $300 million a year.

With around $670 million for sustainment, $225 million for workforce and $300 million for upgrade projects, the Collins class’s direct costs are in the order of $1.2 billion per year.

But since we’re looking at the cost of Australia’s submarine capability, not the Collins per se, we also need to include the cost of the future submarine. Annual spending on SEA 1000, the project designing and building the Attack-class submarine, has been steadily growing. Even though we’re still several years away from starting construction, spending hit $719 million last year and is planned to pass $1 billion this year.

So the direct cost of our submarine capability is around $2.2 billion this year. That’s about 5% of Defence’s $44.6 billion budget. That’s the cost. The fundamental question is whether that presents value. That’s hard to address in one post. Under the Collins’ usage and upkeep cycle, that spend results in two deployable boats. But in light of the long transit distances to where our submarines operate, that model can’t ensure one boat on station. On the other hand, even the prospect of encountering one capable submarine can generate significant uncertainty for any adversary.

The annual spend is going to increase considerably—and quickly. In the near term, as the future submarine project ramps up and transitions from design to construction, it’s reasonable to assume that its annual cash flow will pass $2 billion by the middle of this decade. It’s important to realise that now that we’re in the era of continuous naval shipbuilding, those costs will never ramp down; we will always be designing and building submarines, so we will be paying something like $2 billion per year (in current dollars) until submarines go out of fashion.

The current round of Collins upgrade projects will wind down, but they will be replaced by the Collins life-of-type-extension program in the second half of this decade. While the LOTE is based on a full-cycle docking, its scope is going to be much larger, including new main motors, diesel generators and electrical distribution systems, so its costs will be much higher. How much higher isn’t clear, although the 2020 force structure plan has a funding line for the LOTE of $3.5–6.0 billion (page 45). It’s hard to see its cost being less than the current program of upgrades, so it’s likely we’ll still be spending at least $300 million per year once the first LOTE installation starts in 2026. The number of submariners will need to keep growing in anticipation of the arrival of the Attack class.

By the second half of the decade, we’re likely to be looking at around $3.5 billion per year for our submarine capability—which will be the same as it is now. That’s still some years before the first Attack class is deployable in 2034 on the current schedule.

In the longer term, costs will continue to grow as the Attack class enters service. Its increased sustainment cost will a major driver. The new submarines will be 40–50% bigger than the Collins and the fleet will be twice as big, so the sustainment cost will be at the very least three times that of the Collins—or around $2 billion (in today’s dollars) by the time all 12 boats are in service in the mid-2050s. Defence’s own numbers support this. It has informed the Senate that the sustainment cost of the Attack class will be $50 billion in current dollars; for a 25-year life of type, that works out at $2 billion per year.

Of course, the 2050s are a long way away. But there’s likely to be a 10-year period from the mid-2030s to the mid-2040s when we’ll be operating both the Collins and Attack submarines simultaneously, and that will bring significant overheads.

The future fleet will likely need more than twice as many submariners since the crew of each Attack-class boat will be bigger. Plus, overheads will increase—for example, through the establishment of a second submarine base on the east coast (see page 120 of the 2020 force structure plan).

So, between the operating cost of the future fleet and the ongoing cost of continuous shipbuilding, we could easily be looking at $5 billion per year in current dollars once we reach the mature Attack-class fleet. That’s more than twice as much as we’re paying now, but it should result in at least twice as many boats with greater capability available for operations, meaning more boats will be on station for longer.

Managing risk in the submarine transition: the latest on the Collins life-of-type extension

The Royal Australian Navy is in the early stages of a long transition that is notable for its strategic risk. Both its core surface and subsurface combat fleets are ageing but are planned to be replaced by vessels that are still in the design phase and are years away from entering service. Many commentators have remarked on the capability risk presented by replacement schedules that are better suited to an era of strategic stability rather than our current one of growing instability and uncertainty. Not only does the current plan not increase capability for a decade or more, but it also provides little margin for error in simply avoiding a capability gap as the existing fleets age out.

Some transition risks are already being realised. The overly ambitious ‘cut steel’ date for the first Hunter-class frigate has already been moved from 2020 to 2022, but the Defence Department has been indicating for some time, both at Senate estimates hearing and in its own reporting to the government, that even that schedule is under pressure. Defence’s acknowledgement that the weight of the frigates has grown substantially from 8,800 to 10,000 tonnes confirms that the integration of new weapons, sensors, combat management systems and helicopters into what was already an immature reference ship design is difficult. That lends credibility to recent media reporting that the government has agreed to delay the start of construction even further to 2024. That likely means that the entry into service of the first vessel will also be delayed from the planned date of 2031—and the Anzacs will have to serve even longer, probably well into their thirties.

So far that doesn’t seem to have generated much interest for a ‘Plan B’ for the frigate transition, but there has been much discussion of a Plan B for submarines. Originally that occurred outside of Defence, but it’s become increasingly clear that the problem is being considered inside Defence. But it’s a very confused and contested space. Let’s assess what we’ve learned over the first half of the year.

Plan A for the future submarine program currently involves an Attack-class submarine entering operational service every two years from 2034. Since there will be 12 boats, the final one won’t be operational in the mid-2050s. Because the first Collins-class submarine is due to retire in 2026, followed by a sibling every two years, the fleet would be down to one boat by the time the first Attack-class boat arrived. That’s why Defence has been planning to extend the life of the Collins fleet to give it a further 10 years of service.

That’s the first confusion to clear up. The Collins life-of-type extension is not a Plan B as some have suggested—it is an unavoidable, essential element of Plan A. It’s already built into Defence’s transition planning. The key decision for Defence and the government was not whether to do a LOTE or not, but whether it would focus on availability or capability. If the former, they could minimise the technical and schedule risks but ensure they kept submarines in the water. If the latter, they could seek to enhance capability but run the risk of having boats in sheds as technical risk materialised and upgrades schedules blew out (see here and here).

Since Defence virtually always prioritises quality over quantity, it’s already picked its sweet spot on that spectrum, stating at Senate estimates, for example, that it intended to preserve the Collins as a ‘regionally superior’ capability until their retirement and insisting that the technical risk of doing so was manageable.

In short, despite some media commentary suggesting that new Defence Minister Peter Dutton was going to make Defence do a robust LOTE, the department had already been preparing for a substantial upgrade for several years, including three of the five major systems on the Collins (main motor, diesel generators and electrical distribution systems). In essence, Defence is aiming for a ‘son of Collins’.

It’s possible that Dutton could push Defence to go further, but replacing the remaining two major systems would entail significant risk. The first is the weapons handling system. Some kind of ‘mega-tube’ such as Sweden has installed on its submarines that could launch and recover larger uncrewed underwater vessels would certainly have its uses, but it would probably require a complete redesign of the front end of the submarine. The final major system is the batteries. Dutton could direct Defence to use an early LOTE as a test bed for a lithium-ion-powered submarine, but considering Defence’s consistent rejection of the idea of putting lithium-ion batteries in the first batch of Attack-class boats because it sees the technology as immature (despite Japan having installed them in two Soryu-class submarines already), he would have to overcome significant resistance from the department.

The other confusion to clear up is the view that, because the government hasn’t made any formal announcements about the LOTE, Defence has done little or no work on it. It’s been clear from numerous Senate estimates hearings that design work for the LOTE is well underway. What’s new is that the government has now committed to acquire the first set of equipment for the LOTE. ASC has confirmed that those systems have been ordered for the first boat. It’s not clear why the government hasn’t made an announcement about this, instead allowing public confusion over the status of the LOTE to reign, but it seems to have given up in general on sharing with the Australian parliament and public what Defence projects it has approved. That doesn’t help build confidence in the overall submarine transition plan. Nevertheless, preparation for the LOTE is well advanced.

Of course, that doesn’t mean it will all go smoothly. The greater the scope of the upgrade, the greater the technical risk. So, it’s extremely strange that ASC also stated that it hadn’t yet engaged with Saab. Not only is Saab the designer of the Collins class, but it has just put Sweden’s own submarines through a very extensive upgrade. If you were planning to put your own Swedish-design pedigree submarine through an extensive and technically risky upgrade, wouldn’t the first thing you’d do be to talk to the people who have just done the same thing and identified and mitigated a lot of the risks already?

In fact, there are already some hints that the scale of the LOTE might be overly ambitious; ASC indicated in June that some scope has been moved out of the ‘core package’ into later tranches for which design work has not commenced. As more technical risks materialise, impacting cost and schedule, it’s possible that more scope could move off into the future and potentially never be delivered. The sooner Defence and ASC can draw on Saab’s experiences, the better.

The other new news with the LOTE, again according to media reporting rather than any formal announcement, is that the government has decided it will put all six Collins through LOTEs. That makes sense, but it was already a foregone conclusion if the government wanted to avoid a capability gap. Indeed, over time as the Attack-class schedule has developed, Defence has progressively changed its messaging on the number of Collins needing to undergo LOTEs from ‘one to three’ to ‘at least five’.

Agreement to six provides some risk buffer against further delays in the Attack class. And even if the future submarines are delivered on time, doing all six Collins means more capability at a time when we desperately need it, plus having more submarines gives the navy the capacity to train the much larger number of submariners that will be needed for the future fleet. But it’s important to note that even if the LOTE and Attack-class programs are delivered on the current schedule, the navy will be capped at eight submarines until nearly 2050 unless it finds a way to accelerate the build of the Attack boats.

Agreeing to upgrade all six Collins also provides more certainty to industry. The Collins are meant to get similar main motors and diesel generators (made by Jeumont and MTU, respectively) to the Attack class. That means industry is now supplying a combined Australian submarine program of 18 boats, which is likely the largest submarine program in the western world outside of the United States. That creates the economies of scale needed for overseas suppliers to establish production facilities here. If Defence isn’t seeking to assemble those three main systems here, parliament should be asking why.

On the location of the LOTE, there’s nothing new to report. The government refuses to announce whether it’s going to move the site of Collins full-cycle dockings (and by default the LOTE, which is essentially a more comprehensive FCD). With Defence and ASC having done all the analysis they can on the pros and cons of Adelaide versus Henderson, the only explanation is that the government is saving its decision up for an election campaign announceable.

So, now that we’ve gained a little more clarity on Plan A, what about Plan B? I’ll look at that in my next post.

Why does Australia need 12 submarines?

The following extract is from ASPI’s latest special report, Submarines: Your questions answered, which attempts to answer the many questions that Australians pose when it comes to the design, acquisition, cost, operational service and strategic implications of submarines.

There’s a common rule of thumb in militaries known as ‘the rule of threes’: for every three platforms you have, you can deploy one. This is how the Australian Army is structured, and it broadly applies to ships and aircraft as well. Militaries can surge beyond this for short periods, but that’s not sustainable in the longer term due to deferred maintenance, lack of training, burnout of personnel and so on.

The rule of threes is reflected in the Royal Australian Navy’s current requirement for submarine availability. Of the six Collins-class submarines, two are in deep maintenance and upgrade. Four are available for service, with three available for tasking and one in shorter term maintenance. Of those four, only two are deployable.

The RAN’s submarine requirement: two from six

Source: John Coles, Study into the business of sustaining Australia’s strategic Collins class submarine capability: beyond benchmark—May 2016, Australian Government, Canberra, 2016, page 5.

That doesn’t mean two will always be in the area of operations. Since the likely areas for submarine operations are far from Australia, a large percentage of any deployment is spent in transit. The exact percentage depends on the distance, the kind of operation and so on, but the net result is that it’s unlikely that the navy can sustain one submarine on station in an area such as the Malacca Strait or the South China Sea for an extended period. If, in a future conflict, the operational concept isn’t to maintain a submarine on station but to conduct offensive operations at a time of our own choosing, it might be possible to surge to two submarines in the area of operations, but that couldn’t be sustained.

The requirement for 12 submarines first appeared in the 2009 defence white paper. It wasn’t driven by the Department of Defence but appears to have come from then Prime Minister Kevin Rudd. Since then, it has remained a constant in Defence’s strategic planning documents.

With 12 submarines, it’s reasonable to assume that four would consistently be available for operations, with greater capacity to surge. That would be likely to allow the navy to keep one submarine on station at a long distance from Australia while simultaneously supporting some presence closer to home.

There are factors that influence presence and time on station other than just numbers of submarines. Increasing the endurance of the submarine could potentially have a large impact. The Collins is reputed to have around 50 days’ endurance. If, for example, a 10-day transit is required to reach the area of operations, a Collins boat effectively has only 30 days on station. If the future submarine has 70 days’ endurance (a 40% increase), that would result in 50 days on station in the same scenario (a 67% increase). Put another way, two Attack-class submarines would provide greater presence than three Collins. Also, if the pump-jet propulsor that’s to be used in the Attack class can increase its transit speed without consuming more fuel, that could reduce transit times and further increase time on station.

Since nuclear-propelled submarines have much greater transit speed than conventional submarines and endurance constrained only by the crew’s resilience, a smaller number of nuclear submarines would provide greater presence than 12 conventional submarines.

Another factor is the Attack-class submarine’s pump-jet propulsion system. While Defence has been tight-lipped about the pump-jet’s performance, it could potentially result in greater time on station by reducing transit times.

Reductions in the amount of time spent in maintenance would also improve availability. However, the Collins submarines are now already meeting and exceeding international benchmarks, so it could be difficult to achieve significant improvements beyond the current availability requirement and thus escape the rule of threes.

The strange submarine saga: strategy and nightmares

Submarines are a top-of-the-budget answer to a top-of-the-pile nightmare.

The argument for subs lies within the fundamental call on any nation: defend the realm and protect the currency (proving the oldest-profession status of strategists and economists in the state-building game).

Subs touch both bits of the realm–currency injunction: new boats to defend the borders cost a cornucopia ($89.7 billion is the current Attack-class price tag).

While economists reside in gloom, strategists dwell in horrors: dream up the worst possible scenario and then defend against it. Strategy wonks speak of low-probability, high-impact events.

To argue from first principles, submarines are what you have for the ultimate military nightmare—hostile forces coming to harm your territory. It has only happened once in the history of this Commonwealth, a high-impact moment that consumed all else. The 1942 experience is the existential fright that haunts Oz strategy.

Submarines have other uses, yet Australian voters are happy to simplify by embracing the first-principles thought: subs stop a foe from stepping foot on the nation that has its own continent. Date that view from the first decade of federation.

The subs saga began life with Prime Minister Alfred Deakin’s statement on defence in October 1907. Acting on advice from the Admiralty in London—but contrary to Australia’s naval experts—Deakin announced that his government had decided ‘the submarine is probably the best weapon’ for defence of our harbours.

In what became a familiar Oz problem, the future submarine fleet hadn’t been ordered when Deakin ended his second term as PM, in November 1908. Submarines can torpedo the most decisive of cabinets, leaving them divided and far from port. The saga is well into its second century.

Subs always ask Australia how much it wants to spend on insurance. You can make the argument that nearly $100 billion is a lot for one form of indemnity. Or that there are cheaper ways to get what we need.

The cheaper/other ways line comes up against lots of institutional resistance. Not least the military replacement syndrome. You always replace what you’ve got with more of the same, just a better version. The navy loves what it knows and knows what it loves, and always wants to go to sea in ships and boats.

Here at The Strategist, submarines are the gift that keeps on giving. As Andrew Davies noted a while back, we’ve covered the arguments for big submarineslittle submarinesconventional submarinesnuclear submarines and no submarines, and the claim that we’ve chosen a preposterous submarine.

I’ve been writing about subs and Canberra since well before the Collins class was a gleam in Kim Beazley’s eye. And while geography doesn’t change, the way strategists think about what we might face in the sea–air gap has certainly evolved.

Once, the nightmare was Indonesia. In the same way we had F-111 fighter bombers so we could bomb Jakarta, we got subs to stop Jakarta coming to us. Australia signed up the F-111s in 1963, the same year the navy ordered the Oberon-class boats. The Cold War was the context, but Indonesia was the danger.

Indonesia, as always, looms with the inevitability of geography. It’s still the case, as Paul Dibb put it, that ‘the archipelago to our north is the area from or through which a military threat to Australia could most easily be posed’. That’s an argument for embracing and knowing and loving the archipelago, not just building submarines.

President Joko Widodo was stating aspiration as well as noting geography with his Canberra speech in February: ‘Australia is Indonesia’s closest friend.’

When we got the Oberon class and then built the Collins last century, China was a wisp of smoke on our strategic horizon, and the insurance was against Indonesia. Slowly we have shifted to the possibility of Indonesia as friend and shield, not threat. Intentions can change, but this century Australia has warmed to the idea that the nightmare will come through, not from, the archipelago.

By 2009, when Prime Minister Kevin Rudd embraced a dozen new subs, it was all about China. And China keeps looming larger. In the 2020 strategic update (as in the 2009, 2013 and 2016 white papers), China supplants Indonesia to take second spot in the hierarchy of countries most mentioned.

The strategic update is relatively blunt, as a policy statement, in talking about what Australia fears. Goodness knows what the secret version is like, given the darkness of the public document.

In the canons of Defence, it’s huge that we are scrapping the 50-year-old doctrine that we’d have 10 years’ warning of a state preparing to invade/harm/attack Oz. No longer do we have the comfort that it’d take a potential adversary 10 years to prepare and mobilise for a war that’d reach us. A fundamental change of Defence theology speaks of a mighty disturbance in heaven.

Scott Morrison shares elements of the submarine saga with Alfred Deakin: time available tangles with threat possibilities, seeking answers about the technology and the terrain. Complexity battles with cost.

Canberra is seized by the worry that it hasn’t got enough insurance. Our policy payments mount, but the coverage we want from the Attack class will arrive closer to 2040 than 2030. The new submarine is vital yet vexed, a wicked problem for Australia in what loom as wicked days.

The strange submarine saga: Son of Collins to son of Collins

The switch from creating a ‘Son of Collins’ to making a ‘son of Collins’ is a conundrum of Australia’s submarine saga.

The Defence Department abandoned the option of building a second generation of the Collins-class submarines long ago. And our partner in building the Collins, Sweden, wasn’t even considered in the contest (between France, Germany and Japan) to create the new submarine.

Yet today we are building a new version of the Collins through a life-of-type extension of the existing subs. After casting off the capital ‘S’ option we now clasp the small ‘s’ son of Collins.

The 2020 force structure plan says the cost of the son of Collins—extension plus sustainment—will be between $3.5 and $6 billion. In the way of subs, expect that $6 billion figure to grow. Insight Economics estimates the life extension for the Collins could cost $15 billion.

The sub option that didn’t fully surface is the Son of Collins, although it’s conning tower is visible as the son of Collins. Many factors fathered the decision not to do the Son.

First, politics, with its dimensions of dollars and debate, dithering and delay.

Second, the agonising process of turning the Collins from dud sub to beaut boat. The Collins sustainment was on Defence’s list of projects of concern for a record nine years.

Third, the quarrelsome marriage with Sweden. The legal battles over submarine intellectual property had divorce-court elements: a rerun of the relationship problems conducted as an argument about property and progeny.

Fourth, Defence’s fears about getting the expertise for the evolution to a next-generation boat. Subs need the right minds as well as lots of money.

On the politics of dollars and dithering, Labor’s defence policy platform when it won office in 2007 proclaimed that it’d accelerate work on Australia’s next generation of subs ‘ahead of the current timetable which schedules first pass approval for 2011’. Instead, we missed that target by five years. The Turnbull government did first pass in 2016.

Labor policy in 2007 thought ‘a developmental project involving the migration of evolved Collins class combat and ship control systems might be necessary’. By the 2009 defence white paper, Labor proclaimed the need for 12 new subs.

The stage was set for the Son of Collins. Yet zip happened. The first-pass window kept passing. The global financial crisis hit. Struggling to fix the Collins, Labor didn’t have the energy for the Son and adopted a son stop-gap.

If Labor didn’t act on a Son of Collins, the Liberals couldn’t or wouldn’t. The Libs made much noise about the Collins problems and Labor failures. When Tony Abbott won government in 2013, the Collins was more political pariah than the potential parent of the next-generation submarine. (For this chronology, see the parliamentary library’s new account of the subs story, building on its previous report from 2012.)

Beyond the politics, the conundrum centres on the thinking in Defence and the Royal Australian Navy. Why didn’t the navy want a Son of Collins? Why didn’t Defence put Sweden in the mix?

On those two questions, Marcus Hellyer (ASPI’s sage on the inner workings of the Defence mind) judges that excluding the Swedes ‘is one of Defence’s most bizarre capability decisions’. Bizarre, indeed.

Defence argued there’d been a hiatus in Sweden’s sub building and that gap posed an unacceptable risk. The claim that the game had moved far and fast was also deployed to attack the Son of Collins—developing what we had wouldn’t deliver what Defence said we needed: a brand new design.

As Hellyer writes: ‘Defence testified that a study into the possibility of evolving the Collins “demonstrated that the design effort involved would be similar to a new design”. Ultimately Defence concluded that an evolved Collins “would not provide a beneficial, nor a low cost and low risk solution for the Future Submarine”.’

Australia had the intellectual property for the Collins, but seemed to doubt its intellectual and technical ability to create a Son of Collins. Defence feared we didn’t have the critical mass of expertise to design and build a new boat.

Naval sage James Goldrick emphasises an old line offering a difficult truth: ‘The greatest restriction on naval expansion is draughtsmen not money’.

Canberra worried that it had the money but not the minds. That informs the whispered response to the criticism that Australia should be running a competition between a Son of Collins and the French-designed Attack class. Defence fears it’ll be fiendishly difficult to get the skills and smarts to achieve just one boat design.

As Goldrick told me:

The French may have realised the potential benefit to themselves of this process earlier than anybody else—apart from the fact that their boat was the best, according to the final Australian evaluation.

What is happening all over the world is an increasing problem of continuity for the evolution of design because that requires there to be continued work. Almost nobody is building enough submarines, frequently enough, to be self-sustaining as a centre of design and enterprise.

Even if you are building continuously, if you have a big break in your design effort, it’s very difficult to recover, as the British and even the Americans and Russians have experienced.

Association with the Australian continuous build/batch upgrade scheme would help the French maintain critical mass and sustain their design skills.

So, the Son of Collins didn’t surface. But the stretching Attack-class timeline means we’re now committed to the son of Collins. The saga has many bizarre twists.

Australia’s Attack-class submarines need competition

Australia’s strategic circumstances over the next few decades will mean we cannot afford to be without a submarine capability.

But that’s an area in which we are terribly vulnerable. Serious concerns have been raised over both the ability of the future submarine program to produce the Attack-class boats and the time it will take to comprehensively upgrade the Royal Australian Navy’s Collins-class submarines so that we avoid a capability gap.

It’s time to consider the proposal put forward in the new report by Insight Economics, Australia’s future submarine: Do we need a Plan B?, which I launched last week at the National Press Club.

The report, commissioned by Australian businessman Gary Johnston, notes that the Commonwealth opted for the French primary contractor, Naval Group, before the preliminary design was finalised, before the project could be costed and before there was any solid basis to produce a really tough contract. So matters like cost, schedule, performance and Australian industry participation weren’t spelled out. All of those key issues will be resolved between Naval Group and the Commonwealth without the company being under any competitive pressure.

Real problems have already appeared. The outturned cost of the 12 Attack-class submarines has blown out from $50 billion to $80 billion early in the project, and the negotiations for the strategic cooperation agreement took a long time and were clearly acrimonious. Add to that Naval Group’s evident reluctance to commit to Australian content and the nine-month slippage in the very first stages of the design process.

This is the biggest conventional submarine in the world by far and will be very complex to design and build. If the whole process runs on time, the first submarine won’t be in service until the mid-2030s.

The solution set out in the Insight Economics report is for the government to contract the design of an evolved version of the Collins as an alternative to the Attack class.

The two designs would then compete against each another, and the winner would enter a fixed price contract to deliver the boats. This is the proven, successful approach to major projects like this.

There’s no question of abandoning the Attack class at this stage. The aim is to provide competition for it, which the report says can be done for less than $100 million, and without delaying delivery.

The report argues that the lack of competition is the source of many of the program’s emerging risks. And surely any responsible government would adopt this kind of low-cost option to reduce risk once it becomes clear that those risks are otherwise likely to become unmanageably high.

In his comments at the report’s launch, ASPI’s Peter Jennings did the government a great injustice in saying that there is ‘absolutely zero chance’ of it adopting Plan B.

Jennings argued that the problems that have emerged are just routine teething troubles and will soon be sorted out, and that the Attack class is the only boat that can meet Australia’s submarine needs. So, we have no reason to modify the project, and no alternative to do so anyway.

I think both of those arguments are wrong. First, how serious do the problems need to be before the government should take action to head them off? Big changes to major acquisition projects are always painful, so the temptation is to hold off and hope that things will turn out okay, until the evidence to the contrary is absolutely overwhelming.

But we know from long and bitter experience of failure in far too many projects that by the time the problems are beyond doubt, the project is beyond saving. All the ‘lessons learned’ studies agree that the most critical thing in preventing project failure is to act as soon as real problems appear and head them off before they get too big.

Defence is always the last to acknowledge that a project is in danger of failure.

So, my question to people like Jennings who think it’s too soon to take remedial action is, what further evidence are they waiting for? How far will the schedule have to slip, how far will the price have to rise, how far will the Australian content have to fall, before they decide it’s time to act? And how much harder will it then be to salvage the project?

Jennings argues that there’s no alternative because only the Attack class can meet our operational needs. That’s not true. A Collins 2.0 would have the range and capability to operate in and around the South China Sea as well as closer to home. A lot of the work to update the Collins design has already been done by Saab as it bids for a big long-range submarine for the Royal Netherlands Navy.

Indeed, if the Collins 2.0 was fitted with modern batteries, air-independent propulsion and a conventional propeller, it could well perform a lot better than the Attack class with its inefficient pump jet. And there’s every chance it would be a lot cheaper. It would be less technically risky because it would be based on a design we already know well.

No doubt the government is being told by Defence that all’s well with the project and nothing needs to be done. Anyone who’s worked in Defence knows how hard it is for ministers to disregard such advice, but ministers should remember that their predecessors received exactly the same assurances on other projects that went on to fail spectacularly.

The Collins needs a comprehensive life-of-type extension to remain viable while the new submarines are coming into service.

Our submarine capability is vulnerable to delays in the delivery of the new boats or in the completion of the Collins upgrade. There’s a real risk that we’ll end up with a shortfall in the number of boats we have available, either if we find ourselves in a war, or to maintain the current tempo of operations, including the training of crews.

In the longer term, there’s real doubt that the Attack class will do what we need. It’s a very conservative diesel–electric boat with old-fashioned lead–acid batteries and it doesn’t have air-independent propulsion. We may end up with a boat that can’t meet the operational requirements that will be placed on it.

So the other key recommendation in the report is that, over the longer term, we look seriously at moving to nuclear propulsion. And if that is a serious option down the track, we need to start planning for it now, because the challenges involved are immense.