Tag Archive for: air warfare destroyer

Mitigating the imminent fall in the navy’s surface fleet

We’ve had plenty of defence announcements so far this year. Many have rightly focused on Australia’s situation and vulnerabilities as an island trading nation, one whose daily survival depends on the fuel, fertiliser, pharmaceuticals and other essentials imported by sea.

This awakening has been backed by significant announcements for the program for nuclear-powered submarines, a historic increase in the Royal Australian Navy’s surface combatant fleet, and a capability acquisition plan that puts 38 percent of its money into the maritime domain.

From the glossy documents you could be forgiven for thinking that Australia’s naval capabilities have been strengthened in the short term—that our navy can defend maritime trade and project into the region to contribute to our strategy of deterrence by denial.

The perception of growing naval power is only half true, however.

Ten years from now, when Australia’s first Virginia-class nuclear-powered submarine will have arrived and new general-purpose frigates and Hunter class anti-submarine frigates are emerging from shipyards, the country will have its most potent navy in decades.

But before then its naval power will decline, without significant readjustment of its naval posture, and so will its ability to defend maritime trade. Despite the increased spending over the decade, the alarming fact is that for the next 10 years Australia will have the least capable surface fleet it has had in more than 50 years.

The surface combatant fleet, comprising the frigates and destroyers that constitute the backbone of the navy, will increase to 20 in the 2030s and early 2040s. But it will contract until the early 2030s.

Most reviews of the naval surface fleet over the past 50 years have found a need for 16-20 surface combatants. These assessments were conducted before the rapid militarisation of the region, before China became aggressive in the South China Sea, and before Australia was subjected to its economic coercion.

Australia now has 11 surface combatants. HMAS Anzac, one our eight frigates, will decommission this month, reducing the surface combatant fleet to 10. Then in 2026 the fleet will fall to nine, around half the strength recommended by 50 years of analysis—and this in a time of global tension that has been compared to the period before World War II.

How did we get here? It’s a long story that cannot simply be attributed to the current or former government. It is a story of devaluing naval capability, of delaying decisions and accepting risk where the risk was not fully understood.

But the pivotal question is what to do about the widening gap between needs and capability.

The answer is in naval structure, readiness and posture. We must be bold. For the next 10 years, we must maximise the potency, operational readiness and posture of our remaining ships.

This includes maximising their sea time, with alternate crewing and readiness models. Rather than one crew per ship, we may need multiple crews per ship. The Royal Australian Navy has previously trialled that, and the Royal Navy is doing it now with frigates it deploys to the Middle East.

But what about the implications for the challenged naval workforce? If alternate crewing matters enough, we can make it happen. Historic times call for historic approaches.

But we must go further. To maximise the utility of our diminishing naval assets, we should take a leaf out of the playbook of our AUKUS partners and permanently deploy one of the remaining surface combatants to Southeast Asia.

Basing a frigate in Singapore or the Philippines would increase Australia’s presence in the contested South China Sea, maximising our naval potency during the foreseeable capability gap.

While Australia is spending more on naval capability, during the next decade it will have its least capable naval surface fleet.

In times of historic global tension, the government and navy must take bold action to maximise the operational effectiveness of our remaining fleet. The lifelines of the Australian economy and our way of life may well depend on it.

Delivering a stronger navy, faster

Serious risks are being realised in the Royal Australian Navy’s twin transitions in its surface combatant and submarine fleets. As Australia’s strategic circumstances become more dangerous, Defence needs to adopt hedging measures to actively address the capability risks in its acquisition plans.

The government’s recent announcement regarding the acquisition of nuclear-powered attack submarines (SSNs) is about addressing capability risks in the long term, but with delivery of the first future submarine now delayed probably to the late 2030s, in the short to medium term the proposal exacerbates those risks.

My new ASPI report, released today, details an approach to addressing those risks that will:

  • deliver valuable additional maritime capability to the navy significantly earlier than the current plan
  • sustain, and indeed grow, the workforce that will be essential to our long-term ship and submarine plans
  • develop the industrial ecosystem needed for naval construction in Adelaide and nationally
  • provide a timely return on the funding that the Australian government has already planned to invest in naval capability this decade without requiring additional funding.

In order to deliver on the government’s ambitious plans for future shipbuilding capability, the urgent task today is to develop a bridging strategy that delivers short-term capability wins and boosts vital industrial capability. The plan presented in my report does both by offering a viable way forward to an expanded defence capability and industrial base.

Even before the announcement, the mounting delays in the Hunter-class frigate program prompted commentators to suggest building more Hobart-class air warfare destroyers to provide more maritime capability sooner. That concept makes even more sense now.

There’s an urgent need to deliver more maritime combat power before the Hunter and SSN programs deliver. The first Hunter frigate is already delayed to around 2033 and, with the program facing complex integration challenges and vanishing design margins, there are no guarantees that it won’t slip further.

Even when the Hunter starts coming into service, it’s under-gunned for the threat environment of the 2030s: its missile capacity is the most glaring shortfall. With the lethality of anti-ship missiles increasing, its 32 missile cells mean it’s taking a knife to a gunfight. Plus, it’s going to have limited capacity to carry the Tomahawk strike missile, another of the government’s recent announcements. Meanwhile, the navy’s Anzac frigates will have to serve into the 2040s, even though they only have eight missile cells.

The navy needs combat power—and it needs it before the Hunters turn up on the lethargic two-year delivery drumbeat built into the current naval shipbuilding plan.

To deliver that, we need to rebuild the shipbuilding plan. With the cancellation of the Attack-class submarine, the plan to build Australia’s industrial capability is in disarray. Thousands of skilled jobs that were to be created and sustained by that program are indefinitely deferred. However, we can grasp this as an opportunity to deliver military and industrial capability sooner.

We’ve created the foundations of a national naval shipbuilding machine by massive investments in modern, digital shipyards. But under the current plan this enterprise isn’t delivering anything before the mid-2030s besides very lightly armed offshore patrol vessels (OPVs), despite tens of billions of dollars flowing into it this decade. We need to take advantage of this industrial capacity and investment to give the RAN more offensive power well before then.

We need to refocus public debate around shipbuilding towards the original purpose of the shipbuilding enterprise: delivering the maritime capability the navy needs when it needs it to defend Australia. That means adjusting the shipbuilding enterprise’s order book as strategic circumstances demand. The true value of a continuous naval shipbuilding capability is in its ability to switch production between classes and to accelerate builds as necessary.

Rather than locking in particular vessels on a slow and steady drumbeat to guarantee jobs for the grandchildren of current workers, the enterprise needs to protect the Australians currently paying for it. The government’s 2020 defence strategic update says we no longer have at least 10 years of warning time to prepare the Australian Defence Force to participate in major conflict. We simply should not accept that the navy can’t acquire major new combat capabilities over this next 10 years.

There are two parallel near-term shipbuilding approaches, both taking advantage of the production machine that the government has invested in.

ASPI has already discussed the first: building vessels based on the OPV hull but fitted with missile systems and smart autonomous systems—air, surface and undersea. Not every maritime platform needs to be able to do every task and defeat every threat by itself. Breaking this mindset opens new possibilities. An armed version of the OPV that doesn’t pretend to be a multi-role platform but has useful offensive or sensor capabilities looks attractive as a near-term addition to the navy’s lethality that complicates any adversary’s decisions. They won’t be multi-role vessels, which avoids the spiralling complexity and cost we see with the Hunter, but would operate in tailored taskforces with other vessels.

This approach would be part of a broader strategy of making greater investments in the ‘small, smart and cheap’—disaggregated uncrewed or minimally crewed systems that employ autonomous technologies to generate distributed mass and effect.

The second approach—the focus of my report—is the option of building more Hobart-class air warfare destroyers. We’ve already been through the pains and challenges of getting the design right and learning how to build them. While they mightn’t have quite the same anti-submarine warfare capability as the Hunter is intended to have, they’re still very capable anti-submarine platforms. Moreover, their 48 missile cells offer advantages over the Hunter in air defence and strike—and for deploying missiles made in Australia through the emerging guided weapons enterprise. With the design mature and the build process well understood, there’s the realistic prospect of getting a second batch of three Hobarts into service before the Hunter program delivers, the first of them well before the end of the decade.

As with any complex undertaking, there will be challenges, such as managing facilities and workforce between the major shipbuilding programs at Osborne in South Australia and restarting supply chains, but the shipyard was designed to have more capacity than simply producing one frigate every two years. The reason the government retained ownership of the shipyard (and the taxpayers funded its development) was to retain the flexibility to produce different vessels from different designers as required.

Moreover, a new air warfare destroyer program will help generate the ecosystem of skilled tradespeople, designers, engineers, combat systems integrators, project managers and local suppliers that will be needed for the build and sustainment of the future SSNs. It would avoid a cold start to the SSN program and so help mitigate its schedule risks.

For those concerned about what this means for ultimate numbers of Hunter-class frigates, we can be agnostic for now on that issue. But there’s nothing carved in stone that says the magic numbers for the navy’s major surface combatants are three destroyers and nine frigates for a total of 12. In fact, one of the fundamental problems with the current shipbuilding plan is that it locks us into 12 surface combatants until the 2050s—that’s despite the government’s assessment that we’re facing the most demanding strategic period for our country since World War II. Building a second batch of Hobarts would allow us to grow the fleet faster, whatever the final goal may be.

Certainly, major warships such as the air warfare destroyers are expensive, but they’ll be substantially less so than Hunters, in part because they’re significantly smaller and in part because we already know how to build them. Moreover, the $1–2 billion annual spend freed up by the cancellation of the Attack class can be put to good use building maritime and industrial capability. Most importantly, that spend can deliver capability much faster than the Hunter program.

If the national naval shipbuilding enterprise can’t deliver meaningful capability well before 2030, then its entire purpose needs to be reconsidered. Ultimately, delivering actual capability in strategically relevant time frames will address risk as well as rebuild public confidence in the shipbuilding enterprise.

Should Australia’s navy have more Hobart-class air warfare destroyers?

A recent Strategist article by ASPI’s Marcus Hellyer highlighted issues becoming evident with the Hunter-class future frigate as the planned construction date slides another 18 months to mid-2024. A lot of the delay is put down to modifications to the British Type 26 design to accommodate Royal Australian Navy requirements. This has had negative impacts, including increasing the weight from 8,000 tonnes to 10,000 tonnes.

Contributors to The Strategist have previously discussed what makes a frigate a frigate or a destroyer a certain type of destroyer and whether they’re really cruisers. One writer implied that this might be an insider trick to improve the RAN’s capability without the ‘bean counters’ realising it’s happening.

But if we want to increase the RAN’s capability quickly, there already is a vessel meeting most of its frigate requirements—the Hobart-class air warfare destroyer. Simply continuing to build the AWD as the replacement frigate (or whatever you want to call it) may have many advantages over designing a separate platform.

At first glance, the Hunter frigate’s requirements are remarkably similar to the Hobart AWD’s specifications. They have similar missiles and guns, they’re both designed to use the MH-60 Romeo helicopter and both have hull-mounted sonars and towed arrays, so they are roughly equivalent for anti-submarine warfare.

Their dimensions are close. The Hobart class is 146.7 metres long with a beam of 18.6 metres, and the Hunter class is said to be 149.9 metres long with a beam of 20.8 metres. But the weight of the Hobart class is stated as 7,000 tonnes, far less than is suggested for the Hunter class.

The Hunter class is reported to have a range of over 7,000 nautical miles, compared with the Hobart’s 4,500 nautical miles. However, if the reported weight increases in the redesign of the Hunter are to be believed, that range might well decrease.

It’s also assumed that the RAN is comfortable with the AWD’s range for its surface warfare needs. The Arafura-class offshore patrol vessel is an apparent replacement for the Armidale-class patrol vessel, but it’s more like a corvette, so it could be argued that the RAN isn’t losing patrolling capability.

Requirements for the future frigates remain straightforward, but it seems that the implementation of some RAN specifications is causing considerable engineering challenges. The design reportedly needed significant modifications to enable the use of the Australian CEAFAR radar system, the Aegis combat system, US weapons already in Australian service and the Seahawk maritime combat helicopter. The contract also covered any other modifications that might be needed to meet Australian regulatory requirements. The Hobart-class AWD already meets those requirements except for the CEAFAR radar.

It’s not clear why this radar system is essential. The AWDs don’t use it as their air search and detection radar, yet they are considered excellent air warfare fighting platforms.

It can be assumed that the CEAFAR radar is included because it’s Australian made. Its design and installation in the Anzac-class frigates, as documented by ASPI, is a great advertisement to the world of Australia’s engineering capabilities. It fulfilled a dire need for a more effective air warfare system on the Anzacs and greatly enhanced their capabilities.

However, to insist that the system be used because it is Australian seems to be the equivalent of insisting that the South Australian car industry must remain open simply because it’s Australian, regardless of the cost.

The long-term survivability of a technologically advanced company such as CEA Technologies should be guarded as it makes a huge contribution to national security. However, since the future frigate requirements are very close to the current AWD’s capability barring the CEA radar, it seems appropriate to ask how crucial the CEA radar is.

Since the Hobart class is already operational and mission capable, we could start building more AWDs very quickly, potentially on the original timeline for the future frigates, starting at the end of 2022. The design is already done if we resist the temptation to tweak it. Rectifying a few system design or obsolescence issues would be orders of magnitude easier than making the Type 26 modifications.

Australia’s 2020 force structure plan provides $45.6 billion (in out-turned dollars) for the nine Hunter-class vessels. In constant, current-day dollars, that’s in the $30–35 billion range. The final cost of the AWD program will be less than $8.5 billion, but the ‘sail away’ cost of the third Hobart will be around $2 billion, possibly even less than that. Whichever way you look at it, any additional Hobarts will cost less than Hunters. Aside from being a mature design, they will be substantially smaller.

As has been clearly documented, despite a huge increase in defence spending, the navy’s capability is hardly going to increase in the next decade. However, with solid data from the AWD build, one could come up with accurate schedules for building more Hobarts. The RAN could have new vessels sooner, as long as the hard lessons from the original AWD build are learnt.

This would also introduce economies of scale.

Today’s decision to drop the Attack-class submarine and move to a nuclear vessel demonstrates the huge challenges with making major modifications to an existing design. It also acknowledges the difficulties with operating and maintaining unique platforms. Concerns have been rightly raised about the huge logistical cost of the RAN maintaining these unique AWDs. Increasing the number of Hobart-class vessels could reduce maintenance costs per vessel and make it easier to support them in the long term. The government and the RAN made a courageous decision in accepting these realities with the submarines; they should apply such thinking to other platforms.

In for the long haul (part 3): How far can you push an Anzac?

As I discussed in part 2 of this series, the Anzacs are high-quality frigates. They will likely age gradually but gracefully over the next 24 years on their journey to eventual retirement. But the issue of quantity might be more problematic than quality. Often you just need presence: a ship at sea in the right location, whether patrolling a sea lane, monitoring a patch of ocean, or just waving a flag. No matter how good its quality is, a ship can’t be in two places at once.

The Anzacs have become the backbone of the surface fleet. Every day, Anzacs are at sea. The Royal Australian Navy has conducted continuous rotations to the Middle East since 1990 and Anzacs have done around half of those since their introduction into service. Every one of the eight ships in the class has deployed there at least once, and HMAS Toowoomba has gone five times. An Anzac is currently on extended deployment with Indo-Pacific Endeavour 2019.

The navy will be reliant on the Anzacs for a long time to come—it won’t have more Hunters than Anzacs until around 2037. But the Department of Defence and the defence industry will have to address a number of challenges to ensure the navy can continue to get enough Anzacs to sea to ensure the navy has the presence it needs.

Unlike the Collins class, which has very clear public statement of the capability requirement (page 6)—namely, out of the fleet of six, four submarines in service with the fleet commander (three of which are consistently available for tasking) and two consistently available for deployment—there doesn’t seem to be a public statement of what is required of the Anzac class. Defence’s 2018–19 budget statements provide a target for ‘unit availability days’ for ‘major combatants’ (page 63), but that includes all frigates, destroyers and submarines, not just Anzacs.

So it’s hard to know how the Anzacs are currently performing against the requirements, but the Australia National Audit Office’s recent report on Anzac sustainment suggests that despite Defence’s best efforts, some of the challenges associated with ageing platforms are already emerging with the ships.

Defence’s response to the ANAO emphasised that the Anzac class has consistently met the government’s requirements. That’s fine as long as its long-term sustainability is not put at risk to meet the imperatives of the present.

Part of the problem is that the capability improvements I summarised in part 2 impose a cost on the platform. The addition of systems has increased the ship’s weight from 3,600 to 3,900 tonnes and also resulted in a 50% increase in required power generation. Crew size has grown by 20% (from 157 to 192), resulting in a great workload on each ship’s systems. Also, the operating profile has changed; operational tempo has increased from 125 to 150 days per year, for example.

Overall, the result is that the operating profile of the vessels is outside of the initial design intent. Moreover, the current sustainment regime is not aligned with the operating profile. The ANAO reports that consequently the Anzacs have experienced degradation in hull and systems. Spare parts are becoming unavailable and episodes of cannibalisation to get ships to sea have occurred.

The Anzacs represent a significant investment of public funds. In 2016–17 and 2017–18, at $350 million and $322 million, they were Defence’s second most expensive platform to sustain after the Collins (although in the 2019–20, despite the budget estimate growing to $374 million for the Anzacs, they were bumped into third place behind the Super Hornets and the Growlers). But even that investment wasn’t enough; the ANAO reports that the navy couldn’t afford all required maintenance and had to defer some.

Another long-term challenge that the navy will need to address is a broader one than just the Anzacs. While it has reported improvements in its submariner numbers (which is no small achievement in light of the historical challenges it has faced in crewing its submarines), overall the navy’s personnel numbers went down over the three years to 2017–18, even though its allocation under the 2016 white paper has gone up (though the navy seems to have turned that around in 2018–19).

Something had to give. The ANAO report reveals that due to lack of a crew, HMAS Perth was put into extended lay-up at the end of its last scheduled maintenance in October 2017 and a crew isn’t expected to be available until sometime between July 2019 and January 2020. Essentially, it’s up on blocks for two years. With two other ships in upgrade, only five of the eight are available.

None of these issues are insurmountable. Defence’s approach of rolling all upgrades into the one program (the midlife capability assurance program) is sensible, as is its approach of establishing a long-term sustainment partnership with industry known as the WAMA. Defence is now well versed in managing ageing vessels along the bathtub curve of increasing cost.

Getting a larger, well-skilled uniformed workforce will likely remain a challenge. There will be a long overlap—14 years—between the old and new frigate classes. That’s not quite as long as Collins, but it’s still a period during which competition for resources—in particular, people—will need to be managed. The silver lining in the transition will be the extensive commonality between the two, which will help create a flexible workforce pool.

This commonality will also mitigate technical risks. In essence, the Anzac class and the Aegis-equipped Hobart class are already serving as the test bed for the Hunters and developing workforces that can operate and maintain its systems.

Like the Collins, the Anzacs were unfairly tarred in their early days, and the class has come a long way since the accusations of being ‘floating targets’. But as with the Collins, Defence will still have its work cut out for it keeping the Anzac the workhorse of the navy for a long time to come.

In for the long haul (part 2): Can the Anzacs remain relevant?

In part 1, I discussed how the Anzac class of frigates is only halfway through its service life and the last of the class now needs to remain in service until 2042–43 as the new Hunter class is rolled out. The key question, then, is can the Anzacs remain a relevant frontline capability for another 24 years?

It’s useful to distinguish between the quality and quantity of capability. In terms of quality, the Anzac class is a long way from its original infamous ‘fitted for but not with’ configuration. After a series of upgrades (see the table below), the Anzac is now tonne for tonne among the best frigates in the world. And, as noted in the table, further upgrade projects are either planned or underway.

Project number Project title Budget ($ million) Status Broad scope description
SEA 1442 Phase 4 Maritime Communications Modernisation 455 In delivery Modernised communications for the Anzac class including voice and data
SEA 1448 Phase 2A Anzac Anti-Ship Missile Defence 386.8 Delivered Upgrade of the Saab combat management system and installation of an infrared search and track system
SEA 1448 Phase 2B Anzac Anti-Ship Missile Defence 678.7 Delivered Phased array radar system for target indication/tracking and illumination for the Evolved Sea Sparrow missile
SEA 1448 Phase 4A Anzac Electronic Support System Improvements 269 Delivered Replacement of the tactical electronic support mission system for improved passive situational awareness
SEA 1448 Phase 4B Anzac Air Search Radar Replacement 427 Installation has commenced, first frigate complete Replacement of the Anzac’s air search radar with a modern, digital 3D radar
SEA 1408 Torpedo Self-Defence ? ? Minimal details available
SEA 1352 Phase 1 Evolved Sea Sparrow Missile Upgrade 300 approved; 1,000–2,000 unapproved Still in development, no missiles acquired Upgrade to ESSM Block 2 and acquisition of war stocks

Central to its new capability is the anti-ship missile defence program that upgraded the excellent Saab 9LV combat management system and installed the world-leading CEA Technologies’ phased array radar to target the Evolved Sea Sparrow missile against incoming cruise missiles. The upgraded system has performed very well in trials. Australia is also participating in the international consortium that’s producing an enhanced version of the ESSM designed to counter modern supersonic  missiles. This will equip the Anzac, Hobart and Hunter classes. The replacement of the Anzac’s long-range search radar with a version of CEA’s phased array radar has begun.

Taken together, these improvements significantly enhance the Anzacs’ self-defence capability in air warfare and give them some ability to protect escorted vessels. But the lack of the Aegis combat management system and SM-2 long-range air defence missile means that the Anzacs don’t have a true area defence capability; for that, the navy will have to rely on its three Hobart-class air warfare destroyers until the Hunter class frigates come on line. Hypersonic missiles will likely become operational while the Anzac class is still in service and will certainly be challenging to counter, but they will threaten the survivability of any surface ship, not just the Anzacs.

In terms of anti-surface warfare, the Anzac’s five-inch gun is consistent with those of other major surface combatants, but its main anti-ship weapon, the Harpoon missile, is now dated. It has a shorter range than threat weapons and it has neither of the main attributes that contemporary missiles use to overcome ships’ defences—supersonic speed and stealth. The integrated investment program suggests that Defence will acquire a more capable weapon for the Hunters, so it’s possible that it could be installed on the Anzacs. The Seahawk Romeo helicopter provides a useful capability against swarming attacks by small vessels.

Strangely for the navy’s main anti-submarine warfare ship, the Anzac has mixed capabilities in this regard. The Anzacs were fitted for a towed array sonar but they never received it, and there’s no indication in the integrated investment plan that Defence intends to install such a system. Somewhat ironically, the air warfare destroyers do have a towed array, but there are only three of those ships. Again, the situation won’t be significantly improved until the Hunters arrive with their own towed arrays. This shortfall is partially offset by each Anzac’s Romeo, which has a capable ‘active dipping’ sonar. Two helicopters operating in coordination with dipping sonars can make life difficult for submarines. Unfortunately, each Anzac has only one hangar and consequently one helicopter.

The navy has been quietly but effectively progressing its ‘crawl, walk, run’ strategy for the adoption of uninhabited aerial systems. Since some smaller drones could fit alongside a Romeo in the Anzac’s single hanger, they offer the possibility of enhancing the ship’s aviation capability, in particular by providing greater endurance for surface surveillance. But without a second hangar or mission bay, the potential to integrate autonomous systems without giving up the Romeo that is central to the ship’s anti-submarine capability is limited.

The class has recently, or is currently undergoing, upgrades to other systems such as the electronic support and communications suite.

So, the good news is that overall the Anzacs compare well with other small frigates. The bad news is that it will be challenging to keep the capability relevant against likely threats for the next 24 years.

The upgrades have increased the ship’s weight from its original 3,600 tonnes to 3,900. It probably can’t get any heavier, and the air-search radar replacement may be the last substantial physical alteration made to the vessels. A towed array sonar could be an upgrade too far, even if funds were available. It probably won’t be possible to deploy new solutions like lasers on the Anzacs.

The ships’ upgrades have cost over $2.2 billion, though across a fleet of eight that looks like pretty good value for money given that each Hunter-class vessel will cost at least that much. But finding funds for further upgrades could be difficult as the future frigates and submarines absorb more of Defence’s capital budget.

Much of the cost of defence projects is in design and engineering, which remains the same regardless of whether you buy or upgrade one, eight or 108 systems. So as the Anzacs approach retirement, the value for money of a final round of upgrades for a shrinking subset of the fleet may start to look questionable. The last Anzacs may be left to serve out their time with many of the same systems they have now. Such is the challenge with extended transitions.

That trajectory may amount to a relatively graceful degradation, however. The substantial commonalities between the Anzac and Hunter classes, in their radars, combat management systems, missiles and helicopters, will help. The government’s decision to mandate the Saab 9LV combat management system across the navy’s entire surface fleet, for example, means that improvements to it will be fed back into the Anzacs. Similarly, as the potential of CEA’s radars to conduct tasks such as electronic warfare and secure communication is realised, they can also be used to enhance the Anzac.

But the issue of quantity may be more problematic than the issue of quality. I’ll look at that in part 3 of this series.

Smart buyer: just saying it doesn’t make it so

A key metric for the delivery of the 2016 Integrated Investment Plan is the approval of defence procurement projects. However, after years of uninterrupted transparency, the government has stopped disclosing what it approves.

While that could be taken as a sign that things aren’t going well, that’s probably not the case. As best as I can tell, although approvals look to be running somewhat behind schedule, it’s not by much. If anything, the recent pace of project approvals has matched or exceeded historical rates. I had anticipated that the disruption wrought by the First Principles Review reforms would result in severe delays. I was wrong.

What I failed to appreciate, but now understand, is that the reforms to capability development were just a dismantling of the Kinnaird reforms of 2004. Acquisition and sustainment are now back within Defence, internal contestability has been re-established, Finance gets its seat back at Defence’s capability committee, and the detailed paperwork introduced under the Kinnaird reforms has been pared back substantially. Everything old is new again. We’ve even gone back to the old 1990s ‘buy Australian’ policy.

The only major structural change that was genuinely new was the dismantling of Capability Development Group (CDG)—capability development was a consolidated entity at least as far back as the early 1990s. But breaking up CDG was dumb because economies of scale and scope have been lost.

Of course, we now have the ‘smart buyer’ approach, which tailors acquisition strategies to the demands of specific projects. The recent decision to sole-source the Ground Based Air Defence (GBAD) project following a request for information, rather than going to a competitive tender, is an oft-cited example. But acquisition strategies have always been tailored to the problem at hand, and sole-source acquisitions have been commonplace for as long as defence has been buying kit.

For example, a haunting parallel of the recent GBAD decision can be found in the October 1999 decision to sole-source the MU90 lightweight torpedo, truncating the approval process following a request for proposal. Despite the immaturity of the product, and the challenge of integrating the European torpedo onto multiple US designed platforms, Defence thought they knew enough to make the call. It probably didn’t hurt that—like the successful GBAD proposal—the project came with a juicy local-content package.

After languishing on the projects of concern list, the MU90 achieved final operational capability in September 2013, one month shy of 14 years after the decision to sole-source. And, as the ANAO observed, the project experienced a real cost increase that was only accommodated by reducing the number of platforms onto which the torpedo was integrated. As a result, the ADF now has two types of light-weight torpedoes in inventory—with all the duplication of costs that entails.

Now, consider the Air Warfare Destroyer project. The design phase began with a bespoke ‘baby-Bourke’ as the preferred design. Even Blind Freddy knew that the Navantia F-100 was a stalking horse that had only been included because of the Kinnaird rule that mandated an off-the-shelf option. But once the analysis was complete, it became clear that a properly informed analysis of cost, risk and capability favoured the Spanish design. Given the multiple schedule delays and cost blow out experienced with the less-ambitious F-100, imagine where we would be now if we’d truncated the process and sole-sourced the US design. The lesson is that you don’t know what you don’t know.

We shouldn’t fool ourselves about the revised approach. There’s no magic formula to allow essentially the same group of people to make better decisions in less time and with less information. We’ve gone back to the sort of approach that spawned such memorable favorites as JORN, FFG Upgrade, Super Seasprite, HF Modernisation and, yes, Collins.

It’s delusional to think we’ve moved to a new process that’s better in every way than the old one. The world isn’t like that; everything involves tradeoffs. Although some unnecessary work has surely been eliminated, the more crucial factor is that we’ve adopted a different tradeoff between time and risk. Under the Kinnaird system we expended time to reduce risk. Now we accept greater risks to save time.

Those observations aren’t made as criticisms; our current strategic situation justifies an elevated tolerance of procurement risk. I endorse the revised approach. But if that’s what we’re going to do, we need to recognise it and adjust accordingly. Most importantly, we need to marshal sufficient resources to manage the risks we’re shouldering.

Given the massive scale and manifest risk of the planned program, we could devote substantial additional resources to its management and be confident of a positive return on investment. The danger is that recent reforms to Defence have stripped away program management capacity just when the opposite should be happening. With billions of dollars and the strength of the ADF on the line, now is not the time to be penny wise and pound foolish.

Future Frigates—not so fast!

Image courtesy of Pixabay user Wild0ne.

The rumour du jour in defence circles this week is that the planned date for beginning work on the future frigate program has been slipped a couple years, out to 2022. That’s despite a robust defence of the originally mooted 2020 date by the Minister for Defence Industry as recently as three weeks ago. Normally such a slippage would smack of poor project management and raise the spectre of delayed capability delivery to the ADF. But this seems to be a case of prudent engineering fundamentals reasserting themselves.

And it’s not entirely clear that the Department of Defence or Navy would regard this as a setback. A mid-2014 presentation by Navy shows a 2022 start to the build phase (see slide 4). The enthusiasm for a 2020 start seems to have been largely been driven by the politics surrounding workforce considerations down in the Adelaide shipyard, where the Air Warfare Destroyer (AWD) program is winding down and workers are being laid off.

Navy’s 2015 schematic shows the detailed design period extending to the end of 2021. As I’ll explain below, allowing time for careful design work makes sense. In fact, the 2015 slide assumes that the ‘concept, preliminary and detail design’ phase will extend for 7.5 years. From the outside it’s impossible to tell if that timetable’s on track, but there’d have to be a chance that time’s been lost. So even 2022 might result in a compressed process.

But there doesn’t seem to be much downside to a later kick-off, at least from a capability and project management perspective. For a start, the upgrade program to the Anzac frigates is only just winding up, and those vessels are well placed to sail on for a few years yet. So there’s no imperative from a frigate availability point of view. In fact, it will amortise the cost of the upgrade over a few more years of service, making it a more efficient use of taxpayer’s funds.

The more conspiratorially minded among the defence community suspect that the rumoured slip is an effort to play BAE’s Type 26 frigate more firmly into the mix. It’ll probably have that effect, as the other competitors have representative vessels already at sea while the British contender is only just entering production. But I don’t think that’s the main reason. Instead, it’s likely that the realities of the engineering task ahead are sinking in.

None of the competing ships are ‘off-the-shelf’ fits to Australia’s requirement. In fact, there’s probably no such thing, given our stringent maritime regulatory requirements. In the AWD program, changes to meet local regulations led to many changes in the engineering drawings. (See the ANAO’s 2014 report for more detail.) So there’s substantial work to be done to modify foreign designs even if we don’t insist on Australian-unique changes for capability reasons.

And in this case there are most certainly Australian-unique changes that will require rigorous systems engineering work. The indigenous (and very impressive) CEA phased array radar is formally described as a ‘preference’ for the future frigates, but is mandated to all intents and purposes. Given that Minister Pyne has been in Canada spruiking the system to the RCN, it’s not credible that the RAN will get anything else.

None of the three contenders have ever been fitted with that system, and history shows that the required modifications won’t be straightforward. Data from the ANAO and Defence’s own figures show that ‘Australianising’ systems is rarely easy. The CEA radar has been proven on the Anzac frigates, and so might be termed ‘military-off-the-shelf’ (MOTS). And the competing vessels could also be termed MOTS—if somewhat charitably given the likely regulatory changes noted above. But life in defence systems engineering is rarely that simple. Gumley’s second law tells us that MOTS + MOTS ≠ MOTS.

And there’s still some work to be done to sort out what combat system will be fitted to interface between the ships’ sensors and weapons. The Anzacs have the Saab 9LV system, which is very effective. Retaining the CEA/Saab combination would reduce the amount of integration work required. The competition for the combat system comes from the US-sourced Aegis system, which would have the advantage of commonality with the AWDs and with ballistic missile defence. The downside to Aegis would be yet another step of systems integration. Either way, these aren’t things to be rushed. Working slowly and systematically can actually speed things up later (and save money).

There’s a lot more to say about the Future Frigate program, including the pros and cons of each of the contenders. ASPI will air its views on those over the next few months, including the combat system choice. And James Mugg and I will be back on The Strategist next week with some thoughts about the ways in which the government might handle the delay. (Spoiler: a ballistic missile defence capable fourth AWD wouldn’t be silly in the current international environment.) But the rumoured ‘slip’ of a couple of years—if true—actually gives Australia a better chance of delivering an efficient build program when work finally commences.

Correction: a previous version of this post incorrectly dated the Navy presentation slides as early 2015. The error was the author’s.

The defence challenges of the United Kingdom III

HMS Dragon crossing the setting sun during operations in the Middle East.

The Royal Navy stands at a crossroads as work for the 2015 Strategic Defence and Security Review (SDSR) gets underway in the United Kingdom.

It has the framework in place to provide significant flexibility to a government seeking options for action across the spectrum of conflict. But important decisions need to be made, including a commitment to some increases, albeit relatively modest, in funding. The first and most urgent deficiencies to be remedied are in personnel. At 23,000 in naval uniform (7,000 Royal Marines are usually included in the ‘naval service’ total of 30,000, even though they can do little for the manning of the seagoing force), the Royal Navy is too small. David Cameron’s declaration that both of the new Queen Elizabeth carriers will be placed in commission has added an extra urgency to the need for at least 3,000 more personnel.

Furthermore, there are key shortages in various categories—including nuclear technicians, engineers and weapon and sensor operators—which have made it difficult to keep the existing fleet running. These need to be urgently addressed if the navy’s not to be caught with ships it can’t operate—a problem that would be particularly embarrassing if it were to extend to either of the new carriers.

The navy is also arguably over-committed operationally, which worsens the problem of people, particularly their retention. This is a long-standing problem as successive governments, even as they have reduced the number of ships in commission, have been loath to make concomitant reductions in operational deployments – and the Navy arguably too slow to say no to government ambitions.

The RN’s destroyer and frigate force has apparently stabilised at 19. How great a reduction this represents can be demonstrated by the fact that the debate in the mid-1980s was whether an operational strength of 50 such units could be sustained. The multitude of commitments; to the Gulf, the Indian Ocean, NATO and the West Indies to name only some’ suggest that a more appropriate number in 2015 would be in the region of 24.

The numbers/capability trade-off problem has been clearly demonstrated in the Type 45 air warfare destroyer project, which started at 12 ships, reduced to 8 and concluded with only 6 hulls in service. It continues with the Type 26 ‘Global Combat Ship’ in which the ability to operate in a high intensity combat environment; with all this requires in the way of sensors and weapons, and the need to have capacity for future growth; weigh against the need to reduce costs and thereby allow for greater numbers.

The Royal Navy is hoping for 12 ships, but suspects that it may have the program curtailed once more. It was consciousness of the need to contain costs that meant the prime contractor was forced to review the proposed design concept before the navy and the government would commit to it.

There are indications that the RN is moving towards a more flexible approach to hull numbers than it has adopted for the last decade or more. While the importance of high level capabilities continues to be stressed—and has a clear logic in view of the developments in eastern Europe—the order for three additional Offshore Patrol Vessels (OPV), big enough to operate and hanger a helicopter, may show the way ahead. While this order was ostensibly to prevent Britain’s own ‘valley of death’ between the Type 45 and Type 26 projects, it could be continued, with repeat units being ordered to take the OPV strength up to a dozen, or even more.

Those ships, which at over 90 metres in length are quite substantial units, could perform many of the maritime security tasks currently allocated to the frigates, while releasing the larger and more capable surface combatants to operate with the carriers and amphibious groups in fully capable task groups.

Nevertheless, the priority for the RN has to be resolving its manpower problems and it will require the understanding and the support of the government if it is to achieve this. Indeed, all the British armed forces, and the UK Defence organisation as a whole, require a level of commitment from Westminster which has been notably absent during the last two decades.

Britain doesn’t need to return to the relative levels of defence expenditure that prevailed for most of the second half of the twentieth century, but there does need to be a recognition, even in an era of austerity, that more must be done for the country’s defence.

What on earth is going on with the Air Warfare Destroyer program?

The Guided Missile Destroyer - Hobart sits in the shiplift prior to the official launch ceremony.

Three weeks ago, the finance minister announced the third delay, and the fourth get-well initiative, for the beleaguered Air Warfare Destroyer program. In case you’ve lost track, delays and remediation initiatives were announced in 2011 and 2012, and a ‘reform strategy’ was announced in 2014. The vessels will now be delivered between 30 and 33 months late and cost ‘at least’ $1.2 billion more than planned.

According to the finance minister, ‘these ships are costing $3 billion a ship’ which implies a total project cost of $9 billion. Looking at the budget papers released just prior to the announcement, the pre-existing cost of the project was $7.9 billion. Adding $1.2 billion to $7.9 billion yields $9.1 billion—a 15% cost blow out. That’s bad enough, but those aggregate figures conceal the true state of affairs.

Under the alliance, Defence, Raytheon and ASC share the pain and gain relative to a Target Cost Estimate (TCE) for the alliance part of the project. If the target is met, industry participants receive a pre-determined ‘fee’ to cover profits and corporate overheads. If the project’s under-budget, participants share the unspent funds up to the amount of twice the fee. If the project’s over-budget, additional direct costs are shared by all three participants up to twice the fee. Thereafter, the Commonwealth pays all additional direct costs.

Consistent with the alliance contract, the current approved cost of $7.9 billion has four components:

  • $5.1 billion corresponding to the TCE (including a management reserve)
  • an undisclosed amount to cover ‘government furnished’ inputs including the Aegis combat system
  • the ‘fee’ to be paid to the alliance partners if the TCE is met or improved upon (and a ‘procurement fee’ for Raytheon that’s not at risk)
  • a further financial contingency.

Although the latter three amounts haven’t been disclosed, estimates are possible.

While there’s no hard and fast rule for how large contingency should be for a defence project, the Department of Finance suggests 10%-15% for non-developmental defence IT projects. With this as a benchmark, and noting the manifestly developmental components of the AWD project, contingency of around $1 billion seems reasonable—split between the management reserve in the TCE and the contingency held by DMO. Based on commercial margins, the fee for industry participants is probably around 10% of the TCE or $500 million, leaving around $1.6 billion to cover government furnished inputs.

Everything the government says points to cost blowouts in the alliance component of the project. If there are  problems elsewhere they have not been disclosed. This means that the alliance part of the project is in deep trouble. For the overall cost to have blown out by $1.2 billion, the $1.0 billion contingency has been depleted and the ‘at risk’ component of the $500 million originally set aside to pay the industry partners fees has been redirected to cover emergent costs.

Assuming one-third of the contingency was embedded in the TCE, and that Raytheon’s not-at-risk procurement fee was 20% of the overall industry fee, the TCE has been exceeded by an eye-watering $2.3 billion (= $1.2 billion + $0.66 billion + $0.4 billion).

Actually, the situation is probably not that bad. For reasons I’ll explain in a future post, a change to the indexation arrangements for all defence projects back in 2010 gave rise to a funding shortfall that’s embedded into the foregoing estimate. The indexation shortfall—which is beyond the project’s control—could be in the vicinity of $0.5 billion.

But even taking that into account, there’s still been a massive cost blowout, for which the taxpayer will bear 90% of the pain because ASC is government-owned. Every dollar spent directly on the project will continue to be recompensed 100% by the taxpayer, and Raytheon will still receive its ‘procurement fee’ irrespective of performance.

In theory, ‘liquidated damages’ are owed for late delivery. On the basis of the latest reschedule, the Commonwealth could seek damages of around $557 million. Bizarrely, however, under the alliance contract, Defence is liable for 50% of the liquidated damages and the rest is only recoverable against the already forgone ‘fee’. As elsewhere under the alliance, the taxpayer has once again been left carrying the can.

The forgoing analysis raises a number of questions.

First, why did it take so long to understand the extent of the problems? As recently as mid-2014, Defence assessed that there was ‘sufficient budget remaining for the project to complete against the agreed scope’. How can the project’s prospects have deteriorated so dramatically in less than 12 months? Serious questions need to be asked about the level of oversight exercised by Finance (as owner of ASC) and Defence (as both customer and alliance member).

Second, what’s going to motivate the industry partners now that the incentive fee is no more? The Commonwealth has neither carrots nor sticks. Moreover, what assurance do we have that the line between ‘direct costs’ and ‘fee’ has been properly maintained? Ultimately, the demarcation is an accounting exercise that’s open to interpretation.

Although the details of the AWD alliance’s finances aren’t publicly disclosed, we can get a feel for the sorts of big dollars that arise in the shipbuilding sector by looking at Defence’s handling of the future submarine IPT (Integrated Project Team). As explained in Chapter 7 of the 2015-16 ASPI Budget Brief, there are 35 separate contracts at an average annual per-capita cost of $513k for industry participants in the IPT. For example, the services of a combat system sonar engineer cost $778k a year and an industry and business analyst costs $703k. Either the profits and overheads charged by the firms are egregious, or the direct costs being attributed to personnel are egregious—or both. In any case, the payment of such astronomical fees erodes confidence in Defence’s commercial acumen.

Third, and most importantly, how can the taxpayers’ interests be better protected in future domestic shipbuilding projects? According to the Finance Minister, ‘the Government will release an enterprise-level naval shipbuilding plan later this year, which will provide for the long-term future of the Australian naval shipbuilding industry’. Before we double down on domestic shipbuilding, we need something better than the approach taken for the AWD—which, among other shortcomings, made provision for Defence to sue itself.

The British are coming

The British are coming!

Last week, The Australian broke the story of BAE Systems potentially being brought in to fix the troubled Air Warfare Destroyer project. The three-ship build is already well underway in Adelaide, and the project is currently managed through an industrial alliance contract involving government-owned ASC Pty Ltd, Raytheon Australia and Defence.

Approved at a cost of $8.5 billion dollars in 2007, the project has accumulated nearly two years of delays and $300 million in additional costs. A government-initiated review of the project by ex-US Secretary of the Navy Don Winter and former Transfield boss John White recommended a range of measures, including ‘the urgent insertion of an experienced shipbuilding management team into ASC’.

But while the summary of the Winter/White report was announced by government just two months ago, the AWD Alliance had taken steps before that to remedy some of the project’s shortcomings. One of us (Andrew) visited the site at Osborne last week, and it was clear that some good work has been done. Read more